Active Projects

Ocean Edge

Located on a bluff, overlooking the vast ocean, you'll find Ocean Edge. This cozy six-unit condo complex isn't just luxurious, it's all about carefully curated coastal tranquility. It provides a unique feeling of seclusion and sophistication without compromising on the little things! It's more than just a building; it's a way of life. Here, the ocean's rhythm dictates the tempo, and every aspect is thoughtfully designed to offer an unmatched living environment.

Current Construction Progress

Overall Completion

25%

Foundation

Completed

Completed in November '25
Ground & 1st Floor

In Progress

Completion by January '26
2nd Floor

Starting Soon

Completion by February '26
3rd Floor & Roof

Planned

Completion by April '26

Our Construction Journey

September 1st

Site Preparation

Clearing and grading of the construction site completed. All necessary permits obtained and utilities marked.

Site Preparation
September to October

Foundation Work

Concrete pouring for the foundation completed. All inspections passed with excellent results.

Foundation Work
September 8th to November

Sewage Tank

Following foundation work and sets up the plumbing infrastructure, construction involves building underground tanks, tunnels, and connecting lines.

Framing
December 8th

1st Floor

  • All excavation works on the property has been finalized and conforms to the plan.
  • The foundation and walls of the cisterns, pool, are executed.
  • The rough work on the sun deck is done; floor finishing will be done at a later time.
  • Sewage lines have been installed under the floor and in the floor.
  • Around the foundations and floors, the areas are treated with an anti-termite chemical.
  • Sleeve pipes and pipes for rainwater, sewage, and electricity installation are laid on the ground floor and in retaining walls.
  • The retaining wall along the road is executed with the niches for the storage area.
  • The area between the road and the retaining wall has been filled and compacted.
Framing

Final Construction Phases

Interior Partitions & Finishes
Mid April '26

This phase transforms the project’s interior from raw structure to polished spaces.

Exterior & MEP Installations
Early June '26

Fitting out the building with weatherproof envelopes and vital systems.

Boundary Completion
Late July '26

The closing phase of the project; constructing side boundary walls and fences.